Stage payment schedules by project type
Six worked schedules with illustrative values. Use them to agree the shape of your payments, then build the version for your own project.
How to use these
- Fund each stage before it starts, and release it when the work for that stage is done and checked.
- Where a contract would hold a retention, a funded snagging stage covers the completion half of it. Defects that appear after handover remain a matter for the contract’s defects period, not for held money.
- Price any change to the scope in writing and add it as its own stage before the extra work begins.
- Shares are illustrative. The right split follows your quote, not the other way round.
Single-storey rear extension, £60,000
A typical six-stage schedule for a single-storey rear extension with a new kitchen-diner, excluding kitchen units.
| Stage | What it includes | Share | Value | Check before approving |
|---|---|---|---|---|
| 1. Groundworks and foundations | Site set-up, excavation, foundations poured and inspected, drainage connections | 15% | £9,000 | Building control has inspected the foundations and drainage before they are covered. |
| 2. Shell to wall plate | Blockwork and brickwork to full height, steels installed, lintels, cavity insulation | 25% | £15,000 | Steels match the engineer’s drawings; the walls are at the agreed height and plumb. |
| 3. Roof and weathertight | Roof structure, covering, rooflights, external doors and windows fitted | 15% | £9,000 | The building is genuinely dry inside: roof covering complete, glazing in, no tarpaulins. |
| 4. First fix | Electrical cabling, plumbing and heating pipework, internal stud walls, before boarding | 15% | £9,000 | Cable and pipe runs match the layout; photograph every wall and ceiling before it is boarded. |
| 5. Second fix and plastering | Plasterboard and plaster, sockets and switches, radiators, internal doors, floor screed | 20% | £12,000 | Everything that should work does: lights, sockets, heating. Electrical certificate confirmed as coming. |
| 6. Snagging and completion | Decoration, flooring, making good, snag list closed, building control completion certificate | 10% | £6,000 | The snag list is closed and the completion certificate is in your hands. |
| Total | 100% | £60,000 |
Double-storey or wraparound extension, £120,000
The same six stages at a larger value. Bigger projects often split the shell into two stages; this version keeps six for comparison.
| Stage | What it includes | Share | Value | Check before approving |
|---|---|---|---|---|
| 1. Groundworks and foundations | Site set-up, excavation, foundations, drainage, any underpinning or piling | 15% | £18,000 | Building control inspection passed; any piling or underpinning signed off by the engineer. |
| 2. Shell to wall plate | Masonry to both storeys, steels, floor structure, lintels, insulation | 25% | £30,000 | First-floor structure and steels match the drawings; openings in the right places. |
| 3. Roof and weathertight | Roof structure and covering, windows, external doors, rooflights | 15% | £18,000 | Dry inside, roof complete, glazing fitted and sealed. |
| 4. First fix | Electrics, plumbing, heating, stud walls, staircase if included | 15% | £18,000 | Services routed as drawn; photographs taken before boarding. |
| 5. Second fix and plastering | Boarding, plastering, sockets and switches, radiators, doors, screed | 20% | £24,000 | All services tested; certificates confirmed as coming. |
| 6. Snagging and completion | Decoration, flooring, making good, snag list closed, completion certificate | 10% | £12,000 | Snag list closed; completion certificate received. |
| Total | 100% | £120,000 |
Dormer loft conversion, £45,000
Five stages for a rear dormer conversion with a bathroom, after the design and structural calculations have been paid for separately.
| Stage | What it includes | Share | Value | Check before approving |
|---|---|---|---|---|
| 1. Structural steels and floor | Steels in, new floor joists, structural timbers, party wall works where needed | 25% | £11,250 | Steels and joists installed as the engineer’s drawings specify; building control interim inspection passed. |
| 2. Dormer and weathertight | Dormer built, roof covering, windows and rooflights in | 25% | £11,250 | Weathertight means roof covering complete and windows in, not a tarpaulin over the dormer. |
| 3. First fix and staircase | Stud walls, wiring, pipework, staircase installed | 20% | £9,000 | Stair layout matches the approved drawings; services photographed before boarding. |
| 4. Second fix and plastering | Boarding, plaster, sockets and switches, radiators, doors, bathroom fitted | 20% | £9,000 | Lights, sockets, radiators and bathroom all working; electrical certificate confirmed. |
| 5. Snagging and completion | Decoration, flooring, snag list closed, certificates issued | 10% | £4,500 | Snag list closed; electrical, window and completion certificates received together. |
| Total | 100% | £45,000 |
Kitchen renovation, £25,000
Five stages for a kitchen where the builder supplies and fits the units. If you buy the units yourself, pay the supplier on their own terms and use these stages for the installation only.
| Stage | What it includes | Share | Value | Check before approving |
|---|---|---|---|---|
| 1. Strip-out and first fix | Old kitchen out; water, gas, electrics and drainage moved to the new layout | 20% | £5,000 | Pipe and cable routes match the design before anything is boarded over. |
| 2. Units delivered and fitted | Base and wall units installed and checked against the design | 35% | £8,750 | Inspect the delivery on the day it arrives; doors aligned and layout as sold. |
| 3. Worktops | Templating, cutting, fitting, joints finished, sink and taps in | 15% | £3,750 | Joints sealed, sink plumbed and draining, no chips or mismatched grain. |
| 4. Second fix, tiling and appliances | Appliances connected and tested, tiling and splashbacks, lighting live | 20% | £5,000 | Every appliance run; gas and electrical certificates confirmed as coming. |
| 5. Snagging and completion | Decoration, making good, snag list closed, certificates handed over | 10% | £2,500 | Snag list closed and certificates received. |
| Total | 100% | £25,000 |
Bathroom renovation, £12,000
Four stages for a full bathroom refit with new sanitaryware, tiling and a shower.
| Stage | What it includes | Share | Value | Check before approving |
|---|---|---|---|---|
| 1. Strip-out and first fix | Old suite out, pipework and wiring rerouted, waste and ventilation | 25% | £3,000 | Pipework pressure-tested and photographed before boarding. |
| 2. Tanking, boarding and tiling | Waterproofing to wet areas, boarding, floor and wall tiling | 30% | £3,600 | Tanking complete before tiling; tiles level, grout and silicone sound. |
| 3. Sanitaryware and second fix | Bath or shower, basin, WC, taps, shower screen, lighting and extractor | 30% | £3,600 | Everything fills, drains and runs without leaks; extractor and lighting working. |
| 4. Snagging and completion | Decoration, sealing, making good, snag list closed | 15% | £1,800 | Snag list closed; electrical certificate received where new circuits were added. |
| Total | 100% | £12,000 |
Garden landscaping, £18,000
Five stages for a hard and soft landscaping project with a patio, retaining wall and planting.
| Stage | What it includes | Share | Value | Check before approving |
|---|---|---|---|---|
| 1. Clearance and groundworks | Site clearance, excavation, levels set out, waste removed | 20% | £3,600 | Levels match the design; spoil removed as agreed. |
| 2. Bases and drainage | Sub-bases compacted, drainage and ducting laid, footings for walls | 25% | £4,500 | Sub-base depth and compaction checked before paving goes down; drainage runs photographed. |
| 3. Paving, walls and structures | Patio laid, retaining walls built, steps, pergola or fencing | 30% | £5,400 | Paving falls away from the house; walls plumb; structures fixed as specified. |
| 4. Planting, lighting and finishes | Topsoil, planting, turf, lighting, irrigation | 15% | £2,700 | Plants as listed in the plan; lighting tested after dark. |
| 5. Snagging and completion | Site clean-up, snag list closed, maintenance guidance handed over | 10% | £1,800 | Snag list closed; site left clean. |
| Total | 100% | £18,000 |