Stage payment schedules by project type

Six worked schedules with illustrative values. Use them to agree the shape of your payments, then build the version for your own project.

How to use these

  • Fund each stage before it starts, and release it when the work for that stage is done and checked.
  • Where a contract would hold a retention, a funded snagging stage covers the completion half of it. Defects that appear after handover remain a matter for the contract’s defects period, not for held money.
  • Price any change to the scope in writing and add it as its own stage before the extra work begins.
  • Shares are illustrative. The right split follows your quote, not the other way round.

Single-storey rear extension, £60,000

A typical six-stage schedule for a single-storey rear extension with a new kitchen-diner, excluding kitchen units.

StageWhat it includesShareValueCheck before approving
1. Groundworks and foundationsSite set-up, excavation, foundations poured and inspected, drainage connections15%£9,000Building control has inspected the foundations and drainage before they are covered.
2. Shell to wall plateBlockwork and brickwork to full height, steels installed, lintels, cavity insulation25%£15,000Steels match the engineer’s drawings; the walls are at the agreed height and plumb.
3. Roof and weathertightRoof structure, covering, rooflights, external doors and windows fitted15%£9,000The building is genuinely dry inside: roof covering complete, glazing in, no tarpaulins.
4. First fixElectrical cabling, plumbing and heating pipework, internal stud walls, before boarding15%£9,000Cable and pipe runs match the layout; photograph every wall and ceiling before it is boarded.
5. Second fix and plasteringPlasterboard and plaster, sockets and switches, radiators, internal doors, floor screed20%£12,000Everything that should work does: lights, sockets, heating. Electrical certificate confirmed as coming.
6. Snagging and completionDecoration, flooring, making good, snag list closed, building control completion certificate10%£6,000The snag list is closed and the completion certificate is in your hands.
Total100%£60,000

Open the generator for this project type (it starts from its own preset, so adjust the stages to match this schedule)

Double-storey or wraparound extension, £120,000

The same six stages at a larger value. Bigger projects often split the shell into two stages; this version keeps six for comparison.

StageWhat it includesShareValueCheck before approving
1. Groundworks and foundationsSite set-up, excavation, foundations, drainage, any underpinning or piling15%£18,000Building control inspection passed; any piling or underpinning signed off by the engineer.
2. Shell to wall plateMasonry to both storeys, steels, floor structure, lintels, insulation25%£30,000First-floor structure and steels match the drawings; openings in the right places.
3. Roof and weathertightRoof structure and covering, windows, external doors, rooflights15%£18,000Dry inside, roof complete, glazing fitted and sealed.
4. First fixElectrics, plumbing, heating, stud walls, staircase if included15%£18,000Services routed as drawn; photographs taken before boarding.
5. Second fix and plasteringBoarding, plastering, sockets and switches, radiators, doors, screed20%£24,000All services tested; certificates confirmed as coming.
6. Snagging and completionDecoration, flooring, making good, snag list closed, completion certificate10%£12,000Snag list closed; completion certificate received.
Total100%£120,000

Open the generator for this project type (it starts from its own preset, so adjust the stages to match this schedule)

Dormer loft conversion, £45,000

Five stages for a rear dormer conversion with a bathroom, after the design and structural calculations have been paid for separately.

StageWhat it includesShareValueCheck before approving
1. Structural steels and floorSteels in, new floor joists, structural timbers, party wall works where needed25%£11,250Steels and joists installed as the engineer’s drawings specify; building control interim inspection passed.
2. Dormer and weathertightDormer built, roof covering, windows and rooflights in25%£11,250Weathertight means roof covering complete and windows in, not a tarpaulin over the dormer.
3. First fix and staircaseStud walls, wiring, pipework, staircase installed20%£9,000Stair layout matches the approved drawings; services photographed before boarding.
4. Second fix and plasteringBoarding, plaster, sockets and switches, radiators, doors, bathroom fitted20%£9,000Lights, sockets, radiators and bathroom all working; electrical certificate confirmed.
5. Snagging and completionDecoration, flooring, snag list closed, certificates issued10%£4,500Snag list closed; electrical, window and completion certificates received together.
Total100%£45,000

Open the generator for this project type (it starts from its own preset, so adjust the stages to match this schedule)

Kitchen renovation, £25,000

Five stages for a kitchen where the builder supplies and fits the units. If you buy the units yourself, pay the supplier on their own terms and use these stages for the installation only.

StageWhat it includesShareValueCheck before approving
1. Strip-out and first fixOld kitchen out; water, gas, electrics and drainage moved to the new layout20%£5,000Pipe and cable routes match the design before anything is boarded over.
2. Units delivered and fittedBase and wall units installed and checked against the design35%£8,750Inspect the delivery on the day it arrives; doors aligned and layout as sold.
3. WorktopsTemplating, cutting, fitting, joints finished, sink and taps in15%£3,750Joints sealed, sink plumbed and draining, no chips or mismatched grain.
4. Second fix, tiling and appliancesAppliances connected and tested, tiling and splashbacks, lighting live20%£5,000Every appliance run; gas and electrical certificates confirmed as coming.
5. Snagging and completionDecoration, making good, snag list closed, certificates handed over10%£2,500Snag list closed and certificates received.
Total100%£25,000

Open the generator for this project type (it starts from its own preset, so adjust the stages to match this schedule)

Bathroom renovation, £12,000

Four stages for a full bathroom refit with new sanitaryware, tiling and a shower.

StageWhat it includesShareValueCheck before approving
1. Strip-out and first fixOld suite out, pipework and wiring rerouted, waste and ventilation25%£3,000Pipework pressure-tested and photographed before boarding.
2. Tanking, boarding and tilingWaterproofing to wet areas, boarding, floor and wall tiling30%£3,600Tanking complete before tiling; tiles level, grout and silicone sound.
3. Sanitaryware and second fixBath or shower, basin, WC, taps, shower screen, lighting and extractor30%£3,600Everything fills, drains and runs without leaks; extractor and lighting working.
4. Snagging and completionDecoration, sealing, making good, snag list closed15%£1,800Snag list closed; electrical certificate received where new circuits were added.
Total100%£12,000

Open the generator for this project type (it starts from its own preset, so adjust the stages to match this schedule)

Garden landscaping, £18,000

Five stages for a hard and soft landscaping project with a patio, retaining wall and planting.

StageWhat it includesShareValueCheck before approving
1. Clearance and groundworksSite clearance, excavation, levels set out, waste removed20%£3,600Levels match the design; spoil removed as agreed.
2. Bases and drainageSub-bases compacted, drainage and ducting laid, footings for walls25%£4,500Sub-base depth and compaction checked before paving goes down; drainage runs photographed.
3. Paving, walls and structuresPatio laid, retaining walls built, steps, pergola or fencing30%£5,400Paving falls away from the house; walls plumb; structures fixed as specified.
4. Planting, lighting and finishesTopsoil, planting, turf, lighting, irrigation15%£2,700Plants as listed in the plan; lighting tested after dark.
5. Snagging and completionSite clean-up, snag list closed, maintenance guidance handed over10%£1,800Snag list closed; site left clean.
Total100%£18,000

Open the generator for this project type (it starts from its own preset, so adjust the stages to match this schedule)

Frequently asked questions