Loft conversion stages, costs and timings

A rear dormer loft conversion runs through six stages, from scaffold to building control sign-off, over 8 to 12 weeks on site. A dormer conversion costs about £40,000 to £75,000 in the UK. The dormer stage carries the most risk, because the roof is open.

Build this stage plan

Updated 9 November 2026

What are the stages of a loft conversion?

Each stage, its usual share of the cost, what that is on a £45,000 job, and how long it takes on site. Stages often overlap.

StageShareOn £45,000Time on site
1. Scaffold, clearance and survey check8%£3,6001 week
2. Steels and new floor20%£9,0001 to 2 weeks
3. Dormer and weathertight shell25%£11,2502 to 3 weeks
4. Stairs, partitions, first fix and insulation22%£9,9002 to 3 weeks
5. Plastering, second fix and en-suite20%£9,0002 to 3 weeks
6. Fire safety, sign-off and handover5%£2,2501 week

What should you check before you approve each stage?

Approve a stage when it is done and you have seen these. Ask for photos of anything that will be covered up.

  1. 1. Scaffold, clearance and survey check

    Done when: Scaffold up, loft cleared, and the head height and roof structure checked against the survey.

    • A dated, signed survey confirming the head height.
    • A signed party wall award covering every adjoining owner.
    • A Lawful Development Certificate or a planning decision.
  2. 2. Steels and new floor

    Done when: Steel beams set on the walls, and the new floor joists bearing on the steel.

    • The structural engineer’s calculations for the steel actually delivered.
    • Building control’s record of its inspection of the steel.
    • Photos of every joist bearing, before the floor deck goes down.
  3. 3. Dormer and weathertight shell

    Done when: Dormer framed and covered, windows and flashings in, and the loft dry in rain.

    • A hose test, and photos of every upstand and flashing.
    • Written confirmation that the builder’s insurance covers rain getting in during the works.
    • The roof covering guarantee registered in your name.
  4. 4. Stairs, partitions, first fix and insulation

    Done when: Staircase and walls in, cables and pipes run, and insulation fitted.

    • A stair drawing checked by building control before the stair was ordered.
    • The fire plan in writing: every fire door and alarm position.
    • Photos of the insulation with the product label in shot.
  5. 5. Plastering, second fix and en-suite

    Done when: Plastered, the en-suite waterproofed and tiled, and sockets, radiators and doors fitted.

    • Dated photos of the waterproof membrane in the en-suite, before tiling.
    • A photographed leak test before any pipework was boxed in.
    • The electrician’s registration checked on the scheme’s own register.
  6. 6. Fire safety, sign-off and handover

    Done when: Alarms and fire doors tested, the final inspection passed, and the snag list closed.

    • Trigger one smoke alarm and hear every alarm in the house sound.
    • The Building Regulations completion certificate in your hands.
    • A handover pack: electrical certificate, engineer’s sign-off, window certificates and roof guarantee.

How much does a loft conversion cost?

TypeTypical cost
Rooflight, no change to the roof shape£22,500 to £45,000
Dormer, the most common type£40,000 to £75,000
Hip to gable, semis and end terraces£50,000 to £85,000
Mansard£50,000 to £120,000

Not every source says whether VAT is included, so ask each builder. London and the South East can cost 15 to 30% more.

How long does a loft conversion take?

A rear dormer takes 8 to 12 weeks on site, or 9 to 15 weeks with the usual delays. A rooflight conversion can take 4 to 6 weeks, and a hip to gable or mansard 10 to 14.

Do you need planning permission for a loft conversion?

Often not. A loft conversion is usually permitted development if it adds under 40 cubic metres to a terraced house, or 50 to a semi or detached house. A mansard almost always needs planning permission.

How should you pay for a loft conversion?

Agree a price for each stage before work starts, and release it once you have checked the work.

Keep 5% back from the last stage until the Building Regulations completion certificate is in your hands. Without it, the new room is not legally a bedroom.

With Renopay, the money for each stage is held securely until you approve the work.