How to split a job into milestones
Make each milestone a piece of work the homeowner can see and check when it’s done, with its own price. Our free planner can split a quote for you.
For builders · Updated
What makes a good milestone
- Work the homeowner can see and check when it’s finished, such as foundations poured or first fix done.
- A clear list of the work included, so you both know what “done” means.
- A price that matches that work, so each payment follows the work.
- Realistic dates. They’re for planning: a milestone is paid when it’s approved, not on its end date.
Materials you need to buy first
If you need to buy materials before work starts, make them a milestone of their own, early in the job, and describe what they are. The homeowner pays for it before it starts, like any other milestone.
Let us split it for you
Our free stage planner turns a quote into milestones you can copy into Renopay. Our guides show how common jobs are usually staged.
Was this helpful?
Related
Still need help?
Email support@renopay.co.uk from the address on your account. What to include.